§ IC 36-9-27-25. Drains included in flood control projects; exemption from chapter
Sec. 25. Whenever a regulated drain that is subject to this chapter is included in a flood control project approved by the department of natural resources, the drain ceases to be subject to this chapter. The construction, reconstruction, and maintenance of such a drain is the responsibility of the local agency that constructs and maintains the project.
Terms Used in Indiana Code 36-9-27-25
Maintenance: means work on a drain as described in section 34(c) of this chapter for any of the purposes stated in that section. See Indiana Code 36-9-27-2
Reconstruction: means work on a drain as described in section 34(b) of this chapter to correct any of the problems with the drain that are enumerated in that section up to and including the discharge portion of the drain. See Indiana Code 36-9-27-2
As added by Acts 1981, P.L.309, SEC.101.